C172

NGUNDU

STATUS OF PROJECT

Detour clearing
Detour open to traffic
Clearing Project Road 
Benching RHS
Cut to Waste
(Expansive Sections)
Cut to Waste (Widening for Climbing Lanes)
Pipe Culverts
Box Culvers
Upper Subgrade

Subase Dumping

4.5 km

4.5 km

4 km

4 km

0 %

0 %

4 km

4 km

4 km

4 km

Subbase Compaction
G1 Dumping
G1 Compaction
Prime
Tack Coat & AC Surfacing
Initial Road Paint/Signs

Thermoplastic Paint
Final Clearing & EMP Compliance

As-Built Drawings & Final Inspection
 

4 km

4 km

4 km

4 km

1.55 km

0 %

0 %

0 %

0 %

Overall Progress: 76%