C172
NGUNDU
STATUS OF PROJECT
Detour clearing
Detour open to traffic
Clearing Project Road
Benching RHS
Cut to Waste (Expansive Sections)
Cut to Waste (Widening for Climbing Lanes)
Pipe Culverts
Box Culvers
Upper Subgrade
Subase Dumping
4.5 km
4.5 km
4 km
4 km
0 %
0 %
4 km
4 km
4 km
4 km
Subbase Compaction
G1 Dumping
G1 Compaction
Prime
Tack Coat & AC Surfacing
Initial Road Paint/Signs
Thermoplastic Paint
Final Clearing & EMP Compliance
As-Built Drawings & Final Inspection
4 km
4 km
4 km
4 km
1.55 km
0 %
0 %
0 %
0 %
Overall Progress: 76%