C166

Masvingo - Beitbridge Phase 1 & 2

STATUS OF PROJECT

Detour clearing:
Detour wearing course:
Fills:
lower Subgrade:
Upper subgrade:
Culverts:
Subbase Gravel Dumping:
Cement Stabilized Subbase:
Crushed Stone Base Dumping:

100%

100%

100%

100%

100%

100%

100%

100%

100%

Crushed Stone Base Compaction
Priming
Tack Coat
Asphalt Surfacing
Road marking
Lined Drains

Final clearing
Snagging

Thermoplastic Paint
 

100%

100%

100%

100%

100%

100%

100%

100%

100%

Open to Traffic: 40 km

Overall Progress: 100%