top of page
IMG_1193.JPG

C166

Masvingo - Beitbridge Phase 1 & 2

STATUS OF PROJECT

Detour clearing:
Detour wearing course:
Fills:
Lower Subgrade:
Upper subgrade:
Culverts:
Subbase Gravel Dumping:
Cement Stabilized Subbase:
Crushed Stone Base Dumping:

Crushed Stone Base Compaction Priming

Tack Coat

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

Asphalt Surfacing
Road marking
Lined Drains

Final clearing
Snagging

Thermoplastic Paint

 

 

Remaining Works Include:

Phase 1: Lay Byes, Fencing, Channels & Flumes

Phase 2: Bus Stops, lay byes, bell mouths, kerbing, channels, flumes, end treatment, fencing

Open to Traffic: 40 km

Overall Progress: 98 %

CURRENT PROJECTS:

©2018 by Bitumen World. 

Asset 13_300x.png
  • LinkedIn
  • Instagram
  • Facebook

PROUD MEMBER OF THE 

GROUP OF COMPANIES

IAC Dark Blue and Beige.png

Updated: 01/12/2025

bottom of page