C166

Masvingo - Beitbridge Phase 1 & 2

STATUS OF PROJECT

Detour clearing:
Detour wearing course:
Fills:
Lower Subgrade:
Upper subgrade:
Culverts:
Subbase Gravel Dumping:
Cement Stabilized Subbase:
Crushed Stone Base Dumping:

Crushed Stone Base Compaction Priming

Tack Coat

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

Asphalt Surfacing
Road marking
Lined Drains

Final clearing
Snagging

Thermoplastic Paint

 

 

Remaining Works Include:

Phase 1: Lay Byes, Fencing, Channels & Flumes

Phase 2: Bus Stops, lay byes, bell mouths, kerbing, channels, flumes, end treatment, fencing

Open to Traffic: 40 km

Overall Progress: 98 %