C164
Chimanimani
STATUS OF PROJECT
Clearing and Formation
Subgrade
Base Compaction
Prime
Double Seal
Rusitu Bridge
Makondo Bridge 2
Makondo Bridge 3
100%
100 %
90 %
85 %
85 %
100 %
100 %
100 %
Makondo Bridge 4
Guard Rails
Headwalls
Subsoil Drains
JC Highway (re-gravelling & Asphalt)
Lined Drains
Signage
Road Marking
10 %
50 %
85 %
80 %
0 %
50 %
0 %
0 %
Overall Progress: 90%