Chimanimani

STATUS OF PROJECT

Clearing and Formation
Subgrade
Base Compaction 
Prime
Double Seal
Rusitu Bridge
Makondo Bridge 2
Makondo Bridge 3

100%

100 %

90 %

85 %

85 %

100 %

100 %

100 %

Makondo Bridge 4

Guard Rails
Headwalls
Subsoil Drains
JC Highway
(re-gravelling & Asphalt)
Lined Drains
Signage
Road Marking

 

10 %

50 %

85 %

80 %

0 %

50 %

0 %

0 %

Overall Progress: 90%

CURRENT PROJECTS:

Asset 13_300x.png
Asset 10.png

©2018 by Bitumen World. 

Updated: 07/06/2024