C179

Raubex - Staff Village Civil Works 

STATUS OF PROJECT

- Stormwater junction boxes 5 out of 19 Complete 26.3%
- Stormwater grid Inlets to start brickwork 09/11/2021 0%
- Water reticulation 100%
- Sewerage reticulation 99% 
- Kerbing 45%
- Walkways 13%

 

- Main access road, remaining works:
1. Asphalt surfacing 88%
2. Permanent road marking  0%
3. Permanenr Road signs 60%
4.Culvert end treatments 0%
5. Guiding blocks/kerbs at bridges 5%
6.Final clearing of road servitude 85.7%
7.final inspection and snagging 0%

Overall Progress: 65 %