top of page
![itumen Logo.png](https://static.wixstatic.com/media/f05568_3c47ff41edbd430e9c398be263a55e3b~mv2.png/v1/crop/x_0,y_0,w_1024,h_281/fill/w_231,h_65,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/itumen%20Logo.png)
![Pattern 2.png](https://static.wixstatic.com/media/f05568_36c46fe649f64d76b6db4841a86ede65~mv2.png/v1/fill/w_600,h_145,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/Pattern%202.png)
![Pattern.png](https://static.wixstatic.com/media/f05568_4bbdbfd394df4a3d9070fae354e848f7~mv2.png/v1/fill/w_360,h_87,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/Pattern.png)
![20210614_160428.jpg](https://static.wixstatic.com/media/f05568_0cb5a51c9db64427a51b7afcc2daec3a~mv2.jpg/v1/fill/w_583,h_437,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/f05568_0cb5a51c9db64427a51b7afcc2daec3a~mv2.jpg)
C179
Raubex - Staff Village Civil Works
STATUS OF PROJECT
Project commenced 04/05/2021
5 month contract period
Scheduled completion date 03/10/2021.
Housing infrastructure
-
Roads and carparks 100% base and prime; 25mm asphalt remaining
-
Stormwater:
-
Pipelaying 100%
-
Junction boxes 26%
-
Catchpits/gratings 0%
-
-
Water reticulation 100%
-
Sewerage reticulation 99%
-
Kerbing 45%
-
Walkways 13%
-
Main Access Rd remaining works:
-
Road marking
-
Concrete bridge-edge guides
-
200m of asphalt surfacing
-
Road signs 40% outstanding
-
Overall Progress: 65 %