Masvingo - Beitbridge Phase 3

STATUS OF PROJECT

Detour clearing
Detour open to traffic
Clearing Project Road 
Benching/Earthworks
Pipe Culverts
Box Culverts
Upper Subgrade
Subbase Dumping
Subbase Compaction

 20 km

  20 km

 20 km

  20 km

  18 km

2 km

 19 km

18 km

15 km

G1 Dumping
G1 Compaction
Prime
Tack Coat & AC Surfacing
Initial Road Paint/Signs
Thermoplastic Paint
Final Clearing & EMP
Compliance
AS Built Drawings/Final Inspection
 

15 km

15 km

14.9 km

14.6 km

14.5 km

0 %

15 km

15 km

Overall Progress: 78%