Masvingo - Beitbridge Phase 3

STATUS OF PROJECT

Detour clearing
Detour open to traffic
Clearing Project Road 
Benching/Earthworks
Pipe Culverts
Box Culverts
Upper Subgrade
Subbase Dumping
Subbase Compaction

 20 km

  15 km

 19 km

  16 km

  14 km

1 km

 15 km

14 km

10.75 km

G1 Dumping
G1 Compaction
Prime
Tack Coat & AC Surfacing
Initial Road Paint/Signs
Thermoplastic Paint
Final Clearing & EMP
Compliance
AS Built Drawings/Final Inspection
 

10.6 km

9 km

4.4 km

4.4 km

0 %

0 %

4 km

0 %

Overall Progress: 54%