Masvingo - Beitbridge Phase 3

STATUS OF PROJECT

Detour clearing
Detour open to traffic
Clearing Project Road 
Benching/Earthworks
Pipe Culverts
Box Culverts
Upper Subgrade
Subbase Dumping
Subbase Compaction

 20 km

  20 km

 20 km

  20 km

  12.5 km

12.5 km

 20 km

20 km

20 km

G1 Dumping
G1 Compaction
Prime
Tack Coat & AC Surfacing
Initial Road Paint/Signs
Thermoplastic Paint
Final Clearing & EMP
Compliance
AS Built Drawings/Final Inspection
 

20 km

20 km

17.5 km

15 km

14.5 km

0 %

17 km

15 km

Overall Progress: 91%