GOLDEN QUARRY BUS TERMINUS

EARTHWORKS, PAVEMENT, AC SURFACING, KERBING AND STORMWATERDRAINAGE

STATUS OF PROJECT

23 August 2019

TERMINUS

Base compaction 100% complete

Surfacing 50% complete

Drainage 85% complete

Kerbing 85% complete

 

ROAD

Underground Drainage and Kerbing remaining

C105 Concrete footing 2019-06-24 at 10
C105 2019-06-25 at 08.32.51
C105 2019-06-25 at 08.32.35
C105 2019-06-25 at 08.32.46
C105 2019-06-25 at 08.32.30
C105 2019-06-25 at 08.32.24
C105 2019-06-25 at 08.32.18
C105 2019-06-25 at 08.32.12
C105 2019-06-24 at 09.17.09
C105 2019-06-24 at 09.17.15
C105 2019-06-24 at 10.36.40
C105 2019-06-24 at 09.17.05
Golden Quarry 2019-05-28 at 11.29
Golden  jpeg
IMG-20190522-WA0006
Island backfilling
IMG-20190522-WA0004
WhatsApp Image 2019-05-07 at 14.12.49
Golden Quarry
IMG-20190517-WA0002
IMG-20190522-WA0016
WhatsApp Image 2019-05-07 at 14.12.50

UP AND COMING PROJECTS

  • Highfield Roads 

  • Harare Drive – Kirkman to Lomagundi

  • Belvedere and Francis Flats 

  • Chivi – Mandamabwe – Tokwe Road 

  • Marimba Park 

  • Harrisvale Surfacing

  • Facebook
  • YouTube
  • Instagram

©2018 by Bitumen World. 

C105 2019-06-25 at 08.32.24