Chivi - Mandamabwe - Tokwe Road

STATUS OF PROJECT

27km open to traffic

 

27.8km cement stabilised

 

32.3km gravel dumping

 

27.8km primed

 

27.8km Double seal completed

 

7.6km detour in operation

Water bowser and security only on site at present

Ready to go at Chivi
Stock piling
IMG_0383
IMG_0382
Chivi
Fuel Attendant Leaves
IMG_0357 (2)
Bitumen World at Chivi
2019-07-16 at 06.29.39
2019-07-17 at 22.16.00
2019-07-16 at 08.39.14
2019-07-15 at 12.31.36
2019-07-15 at 09.21.19
2019-07-15 at 12.31.28
2019-07-15 at 09.21.20
MECI 52019-06-25 at 12.01.58
MECI 22019-06-25 at 12.02.25
MECI 2019-06-24 at 10.47.28
MECI 3 2019-06-25 at 12.02.27
MECI 4 2019-06-25 at 12.01.49
C160 22019-06-21 at 08.20.07
C160 32019-06-21 at 08.20.03
C160 2019-06-24 at 19.06.39
C160 2019-06-24 at 19.05.41
C160 2019-06-24 at 19.05.16
C160 2019-06-24 at 08.40.22
C160 2019-06-23 at 09.03.12
C160 2019-06-24 at 08.40.19
C160 2019-06-23 at 09.03.07
C160 2019-06-23 at 09.02.48
C160 019-06-24 at 08.40.22
C160 2019-06-21 at 08.20.07