STATUS OF PROJECT
Temporary crossings installed.
Approaches to Nyahode bridge: Northern embankment complete except gabions.
Southern embankment 50%
Tilbury Rd: Slippages complete
Box culvert at Mutambagwari: Piers complete. Awaiting steel
Chinyakata Highway: Earthworks complete. Gravelling 80%
Junction – Nyabemba River: Gravelling complete
Junction – Rusitu: 4km gravelling complete
Nyahodi 4: Piped drift in progress
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |