Chimanimani Permanent Works

STATUS OF PROJECT

18 October 2019

Temporary crossings installed.

 

Approaches to Nyahode bridge: Northern embankment complete except gabions.

 

Southern embankment 50%

 

Tilbury Rd: Slippages complete

 

Box culvert at Mutambagwari: Piers complete. Awaiting steel

 

Chinyakata Highway: Earthworks complete. Gravelling 80%

 

Junction – Nyabemba River: Gravelling complete

 

Junction – Rusitu: 4km gravelling complete

 

Nyahodi 4: Piped drift in progress

WhatsApp Image 2019-10-11 at 10.16.38
WhatsApp Image 2019-10-11 at 10.16.37
WhatsApp Image 2019-10-11 at 10.16
WhatsApp Image 2019-10-11 at 10.16.36
WhatsApp Image 2019-10-11 at 10.16.35
WhatsApp Image 2019-10-11 at 10.16
WhatsApp Image 2019-10-11 at 10.16.34
WhatsApp Image 2019-10-11 at 10.10
WhatsApp Image 2019-10-11 at 10.14.31
WhatsApp Image 2019-10-11 at 10.10.15
WhatsApp Image 2019-10-11 at 10.10.53
WhatsApp Image 2019-10-11 at 10.16

UP AND COMING PROJECTS

  • Highfield Roads 

  • Harare Drive – Kirkman to Lomagundi

  • Belvedere and Francis Flats 

  • Chivi – Mandamabwe – Tokwe Road 

  • Marimba Park 

  • Harrisvale Surfacing

  • Facebook
  • YouTube
  • Instagram

©2018 by Bitumen World.