STATUS OF PROJECT
16 February 2020
Detour
-
13km complete
-
10km open to traffic
Permanent works
-
Clearing of vegetation from fill slopes and verges – 100% complete
-
Extension of pipe culverts 30%
-
Borrow to fill – 50%
-
Selected subgrade layers – 50%
-
Subbase dumped and spread – 38%
-
Crusher run stockpiling on site (26,000t) – 28%
Site Office & Yard
-
Perimeter fence & gates – 100%
-
Site office and lab building – 85%
-
Workshops – 100%
-
Asphalt plant erection – 100%
Other
Ongoing maintenance of 20km existing road either side of the construction zone
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() |