MASVINGO - BEIT BRIDGE

ROAD WIDENING AND REHABILITATION, PRIME AND 40mm ASPHALT

STATUS OF PROJECT

16 February 2020

Detour

  • 13km complete

  • 10km open to traffic

Permanent works

  • Clearing of vegetation from fill slopes and verges – 100% complete

  • Extension of pipe culverts 30%

  • Borrow to fill – 50%

  • Selected subgrade layers – 50%

  • Subbase dumped and spread – 38%

  • Crusher run stockpiling on site (26,000t) – 28%

 

Site Office & Yard

  • Perimeter fence & gates – 100%

  • Site office and lab building – 85%

  • Workshops – 100%

  • Asphalt plant erection – 100%

 

Other

Ongoing maintenance of 20km existing road either side of the construction zone

IMG_9186
IMG_9455
IMG_9452 (1)
IMG_9455 (1)
IMG_9386
IMG_9384
IMG_9213
IMG_9249
IMG_9205
IMG_9204
IMG_9188 (1)
IMG_9067
IMG_9106 (1)
IMG_9098
IMG_9012
IMG_8995
IMG_8980
IMG_8991
IMG_8982
IMG_8974
IMG_8957
IMG_8841
IMG_8840
IMG_8831
IMG_0761
Bitumen Logo
IMG_8822
IMG_8830
IMG_9189

UP AND COMING PROJECTS

  • Highfield Roads 

  • Harare Drive – Kirkman to Lomagundi

  • Belvedere and Francis Flats 

  • Chivi – Mandamabwe – Tokwe Road 

  • Marimba Park 

  • Harrisvale Surfacing

  • Facebook
  • YouTube
  • Instagram

©2018 by Bitumen World.